Body drawing and welding
A 304 or 316L disc is drawn into a body, the base welded, the neck spun and the thread rolled. Double-wall units are vacuum-tested before the powder coat goes on.
Custom water bottle production runs from two workshops: steel bodies are drawn, welded and vacuum-tested in Dongguan, silicone is moulded on the same site. The plant holds 180+ moulds, employs 150+ workers and ships 500,000 pieces a month. Minimum order is 500 pieces per style, sampling takes 7 to 10 days, and production runs 15 to 20 days after you approve the sample.
A bottle body begins as a 304 stainless steel disc drawn into a cup, then drawn a second time to form the shoulder. The neck is spun and the thread rolled into the wall instead of cut into it, so the lid seats without a burr and the rim stays square. Each body is pressure-tested before coating, because a leaking weld shows up later as a bubble under the powder coat.
Silicone bodies and PP lids are moulded in the Dongguan workshop, on the same order and in the same carton as the steel bottles when a range mixes both. Decoration splits by artwork: silk-screen and UV printing carry flat colours, laser engraving leaves a mark that cannot rub off, and water-transfer or heat transfer wraps artwork around a curved body. Cartons hold 40 to 60 pieces depending on the model, in 5-ply board.
Three operations decide your per-piece price and your delivery date, and each one sits on our own floor rather than at a subcontractor.
A 304 or 316L disc is drawn into a body, the base welded, the neck spun and the thread rolled. Double-wall units are vacuum-tested before the powder coat goes on.
PP lids, food-grade silicone seals and collapsible silicone bodies are moulded in the Dongguan workshop, so a cap and its bottle leave on one packing list.
Silk-screen, UV printing, laser engraving and water-transfer wraps run in-house, then the bottle is bagged, boxed or sleeved and cartoned in 5-ply board.
Tooling is the only line on a quotation a buyer can avoid. More than 180 moulds sit on the rack, and a bottle that matches one of them costs nothing to start. A new shell or body mould is US$400 to US$1,200, cut in 15 to 20 days, and it is invoiced once and recorded as yours, so a reorder never pays for it again.
Payment is 30% deposit and 70% against the pre-shipment inspection report, by T/T. The inspection runs to AQL 2.5 with a photo report before the container leaves, so the balance is released against evidence rather than a promise. Published FOB prices sit at US$2.63 to US$8.70 per piece, with 6% off at 500 pieces, 10% at 1,000 and 15% at 3,000.
Every figure below is the one we quote against, not an average across the range.
Four frames from the plant: moulding, storage, the laboratory and the production hall.
Silicone injected under a 100,000-class ceiling
Cartons of 40 to 60 pcs, counted before loading
Migration, retention and leak samples before dispatch
Compression moulding and assembly on one site
Lids, copying an existing bottle, carton counts and call-off stock.
Send your specification, quantity and target market. We reply with a quotation, a sampling date and the carton count within 12 working hours.